Maryville, TN – The City of Maryville, Tennessee, reported steady progress last week on improvements to Carpenters Grade Road, with crews advancing several phases of the construction project.
According to city officials, work included building up the road base, installing drainage systems, and removing sections of an old waterline.
Crews also prepared areas for new curbs and gutters, with some curb installation already underway.
Additional work involved grading the roadway to the correct height, checking elevations, and completing utility connections.
City officials noted that traffic control measures were periodically in place to allow the work to be completed safely.
The project remains ongoing as construction continues in the area.